Start with the population, not the equipment
A containerized plant is sized on two loads — hydraulic flow and organic load — and the hydraulic side starts from the people the plant serves. National practice converts a water-use allowance into a sewage allowance with a fixed rule: the sewage allowance is 90% of the water-use allowance, and the output category and time basis follow the input (GB 50014-2021 §4.1.14). GB 50013-2018 keeps two inputs separate: the residential highest-day water-use allowance (Table 4.0.3-1, 50–320 L per person per day across the zones and city-size bands) and the combined domestic highest-day water-use allowance (Table 4.0.3-3, its own separate bands). Do not mix the residential and combined tables.
Export projects often work from a single national convention instead. British Water Flows and Loads gives 150 L per person per day for the UK; the US EPA figures are about 170 L per person per day as a residential typical, with design often taken as 284 L per person per day. The point is not which figure is right in the abstract. It is that the allowance has to match the project region and be stated before anything is multiplied.
- Confirm the served population, including any growth the site expects.
- Take the water-use allowance for the project region and water-resource zone.
- Apply the conversion rule to reach the corresponding sewage allowance (residential or combined domestic, matching the selected table).
From per-capita allowance to a design flow
The design flow is the population multiplied by the per-capita sewage allowance, but the time basis has to be carried through. The worked example on the population-to-capacity chart uses the residential Table 4.0.3-1 row, Zone 2 medium city, and 120 L per person per day as an explicit assumption inside that band; converted at 90%, that is 108 L per person per day of residential sewage, and a served population of 10,000 people gives a highest-day flow estimate of about 1,080 m³ per day. That figure is a highest-day estimate, not an average daily flow, so it cannot be multiplied directly by the average-day Kz; convert the time basis first or use a peak method for the highest day. The combined domestic Table 4.0.3-3 is not used in this example. The UK table, by contrast, is already a daily sewage flow. Use the sewage flow calculator to apply your own population and allowance.
Where the population is not the driver — an industrial estate, a food plant, a hospital — the flow comes from the water meter or the process brief instead, and the per-capita route is only a cross-check.
Apply the peaking factor Kz
Plants do not receive flow at a steady average. The dry-weather variation factor Kz scales the average daily combined domestic sewage flow up to the peak. GB 50014-2021 Table 4.1.15 gives Kz of 2.7 at 5 L/s, falling through 2.4 at 15 L/s and 1.9 at 100 L/s to 1.5 at 1,000 L/s and above; the standard note allows interpolation between rows, and the linear interpolation we apply is our calculation rule rather than a standard formula. Size hydraulic channels and pipes on the peak; design biological tanks on the average flow, load and solids retention time and make a peak hydraulic check. Use the peaking factor calculator to apply Kz to your average flow.
Two cautions come with that table. The 2021 edition raised these factors: the superseded 2006 edition used values from 2.3 down to 1.3, and much published material still quotes the old set. Separately, the Middle East convention is different again — the Saudi MEWA design guide uses 1.6 for large cities and 2.2 for villages and towns. An export calculation should state which convention it follows.
Check the organic load, not only the flow
A plant can be hydraulically correct and still undersized, because the biology is sized on what the water carries. Municipal sewage concentrations are survey statistics rather than standard values: a 2016 survey of 127 treatment plants across 19 provinces reports the mean in Table 1 — COD of 220 mg/L, BOD₅ of 81.6 mg/L and suspended solids of 148.5 mg/L — and the 80th percentile in Figure 1. Where the site has measured influent data, use it and say so; otherwise GB 50014-2021 §4.2.1 requires the design quality to be established from a survey or from neighbouring towns and gives per-capita design loads, not a typical concentration table.
Industrial wastewater is a separate case. Where a waste stream carries a high organic load — food processing is the usual example — the organic load governs the plant size, and pre-treatment is settled before the biological stage is sized.
Turn the design flow into tank volume
Tank volume follows from the flow and the residence time the process needs: V = Q × HRT. The hydraulic residence time is set per tank duty. GB 50014-2021 gives 1–2 h for the anaerobic tank and 2–10 h for the anoxic tank (2–4 h under HJ 576-2010 for its configurations), with a solids retention time of 3.5–7.0 days where phosphorus removal is the main objective and 10–22 days for simultaneous nitrogen and phosphorus removal. Where extended aeration is used, the Middle East guide gives an aeration time of 18–36 h and a sludge age of 10–30 days. Use the tank volume and HRT calculator to check the flow and residence time you have selected.
Sizing on the peak flow is the conservative choice for tanks that have to pass the peak, while a biological stage designed on load is often sized on the average flow. Whichever is used should be stated, because the two answers differ.
From volume to footprint and container type
Volumes then become a footprint. A single containerized unit covers a design flow of 0.5–10 m³/h, or 12–240 m³/day, and the assembled equipment ranges from about 3 × 1.5 × 2 m to 16 × 3 × 3.5 m depending on capacity. The larger end of that range cannot travel in a standard dry container, whose internal width is only 2.352 m, and it is the width and the height that decide the shipping route rather than the volume.
This is why sizing ends with a loading check rather than a purchase order. The required capacity decides how many units the plant needs; the dimensions of each unit decide whether it ships in a dry container, in an open-top or flat-rack container, or as break-bulk cargo. Only when those two answers agree is the plant ready to be quoted.
Before the number: the buyer risk checklist
A sizing sheet can be arithmetically correct and still miss what the buyer is about to reject. Before the number is fixed, check the answers a supplier has to give in writing:
- Result and acceptance: which discharge or reuse standard applies, at which sampling point, by which test method, and how the performance test is defined.
- Inputs that are still assumptions: the influent sampling point and date, the peak factor, and whether an industrial contribution moves the load away from domestic sewage.
- Selection boundary: why this process and this unit count, and what would make a different process or a civil-works plant the better answer.
- Supply and site interface: what arrives with the unit and what the site has to provide, including the foundation, the connections, the power and the lifting.
- Handover: who runs the plant, what training and manual come with it, and which spares are held.
- Residuals: where the screenings, grit and sludge go, and which rule classifies them.
- Documents: the drawings, the FAT and SAT records and the performance-test protocol that the offer will actually include.
A supplier who answers these in the same document as the sizing calculation has done the work; a supplier who answers them only after the order has left the buyer to discover the boundary. The containerized sewage treatment plant page shows how those answers are written for one product, and the specification article turns them into the list to hand over before a price is fixed.