Sludge dewatering and industrial projects, case by case

Municipal sludge dewatering installations, plus industrial, livestock and overseas projects, described as the projects were documented — the moisture levels before and after dewatering, the daily volume where it was recorded, and the equipment installed at each site.

Municipal sludge dewatering

  • Hubei sludge disposal center — dewatering equipment on site
    Dewatering equipment on site at the Hubei sludge disposal center.

    Hubei sludge disposal center

    The project handles about 300 tonnes per day of municipal sludge at roughly 80% moisture, and is equipped with 6 CXCG-2000 ultra-high-pressure belt dewatering presses plus a low-temperature drying train. The ultra-high-pressure belt presses first bring the moisture down to 65%; the low-temperature drying equipment then takes it below 40%, and the sludge is sent to a power plant for incineration. In 2025 the plant was expanded to about 400 tonnes per day as a demonstration project handling MBR biochemical sludge with organic matter around 65%.

    CXCG · View the belt press range
  • Baoji Shilipu municipal WWTP — dewatering equipment on site
    Dewatering equipment on site at the Baoji Shilipu municipal WWTP (original photo caption in Chinese).

    Baoji Shilipu municipal WWTP

    The project uses 1 CXNG1500 integrated deep sludge dewatering unit. The equipment has a small footprint and is simple to operate, and it takes sludge at 98% moisture directly down to below 60%. The sludge is then transported to a sludge disposal center for treatment.

  • Pingliang Hongyuan WWTP (Gansu) — dewatering equipment on site
    Dewatering equipment on site at the Pingliang Hongyuan WWTP in Gansu.

    Pingliang Hongyuan WWTP (Gansu)

    The project uses a screw press dewatering machine to take 98% moisture down to about 83%, then 1 CXCG1500 ultra-high-pressure belt dewatering press and 1 sludge drying system to take the moisture below 40%, followed by incineration.

  • Guantao No.3 WWTP — dewatering equipment on site
    Dewatering equipment on site at the Guantao No.3 WWTP.

    Guantao No.3 WWTP

    The project handles about 90 tonnes per day of municipal sludge at roughly 80% moisture. 2 standard belt filter presses take the moisture from 98% down to 83%; 2 CXCG-1000 ultra-high-pressure belt sludge dewatering presses then take it to 65%; and low-temperature drying equipment finally takes it below 40%. The sludge is sent to a power plant for incineration.

  • Tianshui Qinzhou WWTP — dewatering equipment on site
    Dewatering equipment on site at the Tianshui Qinzhou WWTP.

    Tianshui Qinzhou WWTP

    The project previously ran 2 standard belt filter presses and produced about 60 tonnes per day of sludge at roughly 83% moisture. 1 CXCG-1500 ultra-high-pressure belt dewatering press was installed to dewater that 83% sludge to below 60%, and the sludge is hauled away for disposal.

  • Jinan Beikong WWTP — dewatering equipment on site
    Dewatering equipment on site at the Jinan Beikong WWTP.

    Jinan Beikong WWTP

    The project uses 1 CXYG2000 integrated deep sludge dewatering unit. The equipment has a small footprint and is simple to operate, and it takes sludge at 98% moisture directly down to below 70%. The sludge is then transported to a sludge disposal center for treatment.

    CXYG · View the belt press range
  • Huanxian WWTP (Gansu) — dewatering equipment on site
    Dewatering equipment on site at the Huanxian WWTP in Gansu.

    Huanxian WWTP (Gansu)

    The front end of the project uses a screw press dewatering machine and produces about 50 tonnes per day of sludge at 85% moisture. 2 CXCG-Y1500 ultra-high-pressure belt dewatering presses are fitted, and the moisture content of the treated sludge drops below 60%.

  • Rizhao Water Group sludge composting project — dewatering equipment on site
    Dewatering equipment on site at the Rizhao Water Group sludge composting project.

    Rizhao Water Group sludge composting project

    The project handles about 200 tonnes per day of municipal sludge at roughly 80% moisture. The sludge at 80% moisture was originally mixed with bulking agent and sent straight to composting and fermentation, which took a large dose of bulking agent and cost a lot. 2 CXCG-2000 ultra-high-pressure belt dewatering presses are now fitted, and the sludge is dewatered to 65% before fermentation.

  • Zaozhuang WWTP (Shandong) — dewatering equipment on site
    Dewatering equipment on site at the Zaozhuang WWTP in Shandong.

    Zaozhuang WWTP (Shandong)

    The project uses 1 CXBC-1550 automatic thin-layer high-dryness filter press. The equipment has a small footprint and is simple to operate, and it takes sludge at 98% moisture directly down to below 50%.

Industrial, livestock and further municipal projects

  • Three 1500-series ultra-high-pressure belt filter presses prepared for shipment to Shandong
    The three 1500-series ultra-high-pressure belt presses before shipment to Shandong (original photo caption in Chinese).

    Three 1500-series ultra-high-pressure belt presses shipped to Shandong

    Three 1500-series ultra-high-pressure belt filter presses were shipped to the Qilu region of Shandong for deep sludge dewatering. The units went out as one consignment for a regional sludge reduction programme.

  • 100 t/d municipal sludge deep dewatering installation in Sichuan
    The 100 t/d additive-free dewatering line at the Sichuan water group plant (original photo caption in Chinese).

    Sichuan water group 100 t/d additive-free deep dewatering

    A municipal sludge deep-reduction project for a water group in Sichuan runs at 100 tonnes per day with no conditioning additives of any kind. The plant has run steadily since it was handed over.

  • Cow-bedding regeneration equipment operating at a Weifang dairy farm
    Cow-bedding regeneration equipment at the Weifang dairy group (original photo caption in Chinese).

    Weifang dairy group cow-bedding regeneration line

    A large dairy farming group in Weifang, Shandong, brought a cow-bedding regeneration line into production. The line turns separated manure solids back into cubicle bedding, and it has reached stable design output.

  • High-pressure cattle-manure dewatering machine on a dairy farm
    The high-pressure manure dewatering machine at the cattle farm (original photo caption in Chinese).

    High-pressure cattle-manure dewatering to below 50% moisture

    A high-pressure dewatering machine on a cattle farm takes fresh manure down to below 50% moisture. At that dryness the downstream fermentation and drying step needs far less make-up work, which the farm reported as a substantial saving on those stages.

  • Cow-bedding regeneration line at a 10,000-head dairy farm in Hebei
    The bedding regeneration line at the 10,000-head Hebei dairy farm (original photo caption in Chinese).

    Hebei 10,000-head dairy farm bedding regeneration

    A 10,000-head dairy farm in Hebei completed and took delivery of a cow-bedding regeneration line. The line returns dewatered manure solids to the cubicles as bedding.

  • 2024-model unmanned municipal sludge dewatering machine on site
    The 2024-model unmanned municipal dewatering machine at commissioning (original photo caption in Chinese).

    2024-model unmanned municipal sludge dewatering unit commissioned

    A 2024-model intelligent unmanned municipal sludge dewatering machine was commissioned. Output moisture holds at 50% with no additives introduced into the sludge.

  • Municipal sludge dewatering equipment at a city plant in western China
    Dewatering equipment at the western China municipal project (original photo caption in Chinese).

    Municipal sludge deep dewatering in a western China city

    A municipal sludge deep-dewatering and volume-reduction project in a city in western China was completed. The plant dewaters municipal sludge as part of that volume-reduction programme.

  • Slaughterhouse wastewater treatment installation rated at 1,500 cubic metres per day in Guizhou
    The 1,500 m³/day slaughterhouse wastewater plant at completion of installation (original photo caption in Chinese).

    Guizhou slaughterhouse wastewater plant, 1,500 m³/day

    A slaughterhouse wastewater treatment plant rated at 1,500 cubic metres per day was installed in Guizhou. Installation finished at the start of January and commissioning began straight away.

  • Vacuum press filter running at a gypsum regeneration project in Hubei
    The vacuum press filter at the Hubei gypsum regeneration site (original photo caption in Chinese).

    Hubei gypsum regeneration project starts up

    A gypsum regeneration project in Hubei started up on a vacuum press filter. The filter dewaters the regenerated gypsum on site as the first step of the regeneration route.

  • Phosphogypsum regeneration dewatering installation in Guizhou
    The delivered phosphogypsum regeneration installation in Guizhou (original photo caption in Chinese).

    Guizhou phosphogypsum regeneration project delivered

    A phosphogypsum regeneration project in Guizhou was delivered and handed over. Delivery was quick and the installation was carried out to specification.

  • 2025-model stacked high-pressure dewatering machine at a 50 t/d Anhui municipal plant
    The stacked high-pressure dewatering machine at the Anhui municipal project (original photo caption in Chinese).

    Anhui 50 t/d stacked high-pressure dewatering below 40% without thermal drying

    A 50 tonnes per day municipal project in Anhui commissioned a 2025-model stacked high-pressure dewatering machine. The machine is applied to municipal, slaughterhouse, farming and paper sludge and takes the cake below 40% moisture without thermal drying.

  • CXBC automatic thin-layer variable-cavity high-pressure dewatering machine in Henan
    The CXBC thin-layer high-pressure dewatering machine at the Henan water group plant (original photo caption in Chinese).

    Henan CXBC thin-layer high-pressure dewatering, 30 days stable

    A CXBC fully automatic thin-layer variable-cavity high-pressure dewatering machine has run for 30 days at a water group plant in Henan. It holds cake at 40% moisture with no thermal drying.

  • Vacuum belt filter at a zircon and titanium dewatering site in Fujian
    Vacuum filtration equipment at the Fujian zircon and titanium site (original photo caption in Chinese).

    Fujian zircon and titanium mineral dewatering

    Vacuum belt filters were dispatched to a zircon and titanium mineral dewatering site in Fujian. The filters dewater the mineral material on site before the next stage of processing.

  • Vacuum filter prepared for shipment to a Heilongjiang thermal power plant
    The vacuum filter before dispatch to the Heilongjiang thermal power plant (original photo caption in Chinese).

    Vacuum filter shipped to a Heilongjiang thermal power plant

    A vacuum filter was shipped to a thermal power plant in Heilongjiang for flue-gas desulfurization dewatering. The unit dewaters the desulfurization slurry on site.

  • CXGY high-pressure belt dewatering machine at a 60 t/d municipal sludge site
    The CXGY high-pressure belt dewatering machine on site (original photo caption in Chinese).

    CXGY high-pressure belt dewatering, 60 t/d at 60% moisture

    A CXGY high-pressure belt dewatering machine runs stably at 60 tonnes per day of municipal sludge. Cake moisture settles at 60%.

  • Vacuum belt press filter supplied to a copper mine in Zambia
    The vacuum belt press filter at the Zambian copper mine (original photo caption in Chinese).

    Zambia copper mine vacuum belt press filter

    A vacuum belt press filter was supplied to a large copper mining group in Zambia. The unit dewaters mineral material in the mine circuit.

  • 100 m³/h dissolved air flotation unit at a Shandong dairy wastewater plant
    The 100 m³/h air flotation unit at the Shandong dairy group plant (original photo caption in Chinese).

    Shandong dairy group 100 m³/h dissolved air flotation

    A dairy group in Shandong runs a 100 cubic metres per hour high-efficiency nano dissolved air flotation unit on its wastewater. COD and suspended-solids removal have stayed steady, and the unit takes out milk fat, protein and emulsified oil so the downstream process does not clog.