Flow and retention time to tank volume, in either direction
The calculator runs V = Q × HRT both ways: flow and a retention band give the tank volume, flow and an existing tank volume give the actual retention time, and an optional depth adds the ground area. HRT is the hydraulic retention time, not the solids retention time.
Result
The tank volume follows from V = Q × HRT, with Q in m³/day and HRT in hours.
Required tank volume
41.7–83.3m³
Flow × HRT ÷ 24. The range is the published band, not a single choice.
Source: GB 50014-2021
Send the flow, the retention time the process is designed to and your depth, and we confirm the tank arrangement.
Data sheet draft
These are catalogue-based figures for your enquiry. Confirm them against your site data and the factory quotation before ordering.
What you entered
- What are you working out?: Size a tank
- Flow Q (m³/day): 1000 m³/day
- Process band: Anaerobic tank — 1–2 h (GB 50014-2021)
What we derived
- Required tank volume: 41.7–83.3 m³
- Source: GB 50014-2021
Still to confirm
- Whether the tank is aerated, in which case SRT and MLSS govern the volume, not HRT alone
- Freeboard, inlet and outlet arrangement, and whether a cover is required
- Material and lining specification for the site soil and groundwater conditions
This is a hydraulic retention volume. Equipment selection for a packaged plant follows flow and load, not this tank volume.
Tank volume at seven flows across the three published bands
Each row is one flow in m³/day, and each column is one published retention band turned into a tank volume with V = Q × HRT. The table is complete in the page source, so it can be read and cited with JavaScript turned off.
Wide table: scroll sideways to see every column.
| Flow (m³/day) | Anaerobic, 1–2 h (m³) | Anoxic, 2–10 h (m³) | Extended aeration, Middle East, 18–36 h (m³) |
|---|---|---|---|
| 100 | 4.2–8.3 | 8.3–41.7 | 75.0–150.0 |
| 250 | 10.4–20.8 | 20.8–104.2 | 187.5–375.0 |
| 500 | 20.8–41.7 | 41.7–208.3 | 375.0–750.0 |
| 1000 | 41.7–83.3 | 83.3–416.7 | 750.0–1500.0 |
| 2500 | 104.2–208.3 | 208.3–1041.7 | 1875.0–3750.0 |
| 5000 | 208.3–416.7 | 416.7–2083.3 | 3750.0–7500.0 |
| 10000 | 416.7–833.3 | 833.3–4166.7 | 7500.0–15000.0 |
Basis: anaerobic 1–2 h and anoxic 2–10 h (GB 50014-2021) and Middle East extended aeration 18–36 h (Saudi MEWA guide). No margin and no depth are applied — the depth is your own site figure and is used only for the ground-area arithmetic. Solids retention time, the anoxic and aerobic split, and the retention time of A/O, MBBR, MBR and SBR are not part of this table; the tank volume and HRT chart states why.
What this calculator does
It runs the tank volume formula in both directions. Given a flow and a retention time it returns the tank volume; given a flow and an existing tank volume it returns the actual retention time and places it against a published band. Enter a depth as well and it returns the ground area of that volume at your depth.
The three bands are the values already published on our tank volume and HRT chart, each with its source, and this page runs the same arithmetic with your numbers. The chart remains the look-up reference, and the links at the foot of the page go to it and to the articles behind the bands.
The formula
V = Q × HRT. V is the tank volume in m³, Q is the flow in m³/day and HRT is the hydraulic retention time in hours; dividing by 24 turns hours into a fraction of a day. At 1,000 m³/day and 2 h, V = 1,000 × 2 ÷ 24 = 83.3 m³.
The reverse gives the retention time of a tank you already have: HRT = V ÷ Q × 24. A 100 m³ tank at 1,000 m³/day holds 100 ÷ 1,000 × 24 = 2.4 h. The ground area is A = V ÷ depth, using the depth you enter.
Basis and assumptions
Every value in the calculator comes from one of the sources below, and each row states which. The bands are the published values behind the tank volume and HRT chart, the formulas are general arithmetic, and the custom retention time and the depth are yours — the page sources neither. A custom retention time is your own figure and we do not endorse it; it is shown beside the three published bands at the same flow so the comparison is yours.
| Parameter | Value | Source | Evidence level |
|---|---|---|---|
| Anaerobic tank HRT | 1–2 h | GB 50014-2021 | National standard clause |
| Anoxic tank HRT | 2–10 h | GB 50014-2021 §7.6.17, Table 7.6.17 and Table 7.6.19 | National standard clause and table |
| Extended aeration, Middle East | 18–36 h; MLSS 3,000–6,000 mg/L and SRT 10–30 d shown as context only | Saudi MEWA guide; official guide, Middle East practice only — not a national standard | Official guide |
| Required tank volume | V = Q × HRT | General formula, as published on the tank volume and HRT chart | General |
| Actual retention time | HRT = V ÷ Q × 24 | The same formula solved the other way | Derived |
| Ground area | A = V ÷ depth | Arithmetic; the depth is reader-supplied | Derived |
| Custom HRT | Reader-supplied hours | Not sourced by us | Reader input |
| Tank depth | Reader-supplied metres | Only used for the footprint arithmetic; the page states no depth of its own | Reader input |
Worked example
A flow of 1,000 m³/day, run through all three bands and then in reverse. Anaerobic 1–2 h gives 41.7–83.3 m³. Anoxic 2–10 h gives 83.3–416.7 m³. Extended aeration, Middle East, 18–36 h gives 750.0–1500.0 m³. At a depth of 3 m — a figure entered by the reader, not supplied by this page — the anaerobic volume covers 13.9–27.8 m². Read the other way, a 100 m³ tank at 1,000 m³/day holds 2.4 h, which is above the anaerobic 1–2 h band and inside the anoxic 2–10 h band. Every figure above is the output of the calculator on those inputs, so each can be checked by hand.
Limits
The calculator returns volumes and hours from the figures you give it; it does not finish the design.
- No solids retention time. SRT needs a sludge-wasting model and is not a function of flow, volume and HRT; the sludge age shown beside the Middle East extended aeration band is context, not an output.
- No anoxic and aerobic split. The standard states no unified split between the two zones, so the page does not divide a tank volume between them.
- No HRT presets for A/O, MBBR, MBR or SBR. Select a displayed anaerobic, anoxic or Middle East extended-aeration band, or enter a project-specific custom HRT.
- No reverse sizing from a product model. A catalogue model is not used to infer a tank volume, and the calculator names no model.
- No specification for chemical reactors. A Fenton reactor figure is a vendor process specification, not a biological tank retention band, and it is not offered here.
- Final sizing is confirmed against the project's measured flows and the designer's review.