| A Baseline audit | Owner supplies production, wasting and destination; manufacturer checks the existing machine; site party checks the site; third party tests as required | Streams, metering boundary and historical data available | Raw flow, TS, operation and gap list | Minimum dataset complete; each gap has a named blocker | Owner fills production and metering; manufacturer fills machine data; do not move on with unclear responsibility | New-machine performance. |
| B Sludge and mechanism test | Owner supplies representative sludge; manufacturer runs the test; third party witnesses or splits samples as required | Target mechanism, polymer, target cake and safety plan agreed | Sample chain, preservation, parallel or split samples, cake, filtrate, flux or cycle and dose | Project criteria met under the target mechanism | Manufacturer adjusts mechanism or polymer; owner resamples if the sludge is not representative; otherwise change route or stop | A jar result or one small test does not guarantee full-scale long-term performance. |
| C Factory acceptance test | Manufacturer executes; owner or third party witnesses as contracted | Actual manufacturing configuration and instrument calibration; protocol frozen | Serial number, configuration, no-load and load tests, safety and control records | Contract FAT clauses, bill of materials and safety and interlock items pass | Manufacturer repairs and retests | Actual sludge performance or site capacity. |
| D Delivery and installation | Site party installs; manufacturer checks requirements; owner organises delivery and custody | Civil works, utilities and maintenance space complete | Delivery, shortage, material and instrument certificates and hidden-work records | Drawings, supply list and installation specification pass and deviations close | Site party corrects installation; manufacturer replaces missing supply; owner completes its utilities | Interconnection or performance. |
| E Clean-water and interconnection | Manufacturer and site party jointly; owner supplies utilities and operators | Installation accepted; electrical, instrument and safety briefing complete | Point-by-point I/O, wash water, alarms, interlocks and fault stop | All agreed I/O, interlocks, wash water and safety functions pass | Defects corrected by the responsible manufacturer or site party | Sludge throughput or cake quality. |
| F Feed start-up | Manufacturer tunes; owner stabilises sludge, polymer and transport; site party closes leftovers | Interconnection passed; cake outlet and filtrate return available | Per-shift or per-batch feed, TS, dose, parameters, cake and abnormalities | Repeatable safe operation; root causes corrected by the responsible party | Manufacturer retunes, owner restores feed and disposal, and the responsible party corrects; repeat the start-up check | Start-up success is not completed performance acceptance. |
| G Performance verification | Owner holds the agreed conditions; manufacturer operates and guarantees; third party or agreed laboratory tests | Stable start-up; protocol, criteria, instruments, split-sample and dispute rules frozen | Agreed continuous period or complete batches covering the normal-unfavourable feed envelope; synchronised flow and weighing, composite and cake distribution samples and raw curves | Capacity, cake, capture, active dose, cycle, side-stream and transport requirements pass together | Data validity judged first; equipment and parameters corrected by manufacturer, conditions and utilities by owner, installation by site party; retest and rejection per contract | Sludge outside the envelope, long-term reliability or untested energy and disposal cost. |
| H Training and handover | Manufacturer trains and hands over documents; owner provides personnel; site party hands over completion records | Performance defects closed or remaining items have an owner and deadline | Practical assessment, SOP, spare parts, drawings and software versions | Personnel can perform agreed operations; documents and spares complete | Manufacturer adds training or documents; owner adds personnel and procedures | Unattended operation or maintenance-free running. |
| I Long-term operation | Owner records and maintains; manufacturer supports under warranty; third party checks as planned | Handover complete; consumables, transport and testing resources available | Weekly and monthly trends, cake weight and transport, filtrate, maintenance and abnormalities | Contract warranty, availability and performance clauses and the legal destination continue to be met | Correct by root cause; a trend limit triggers review rather than hidden data | The initial performance test does not replace long-term compliance or whole-life cost. |