| A Baseline audit | Owner supplies use, permit and records; designer checks timing; manufacturer checks equipment; third party tests as required | Representative high and low days, batches and existing abnormalities covered | Raw flow, quality, equipment state and gap list | Minimum dataset complete; each gap has a named owner | Measure or supply by data responsibility; do not move on with an unclear basis | New-equipment performance. |
| B Necessary test or pilot | Owner supplies representative water; manufacturer or test party executes; third party witnesses as required | Agreed quality, temperature and normal-unfavourable conditions covered | Sample chain, raw curves, effluent, sludge and cleaning records | Project criteria met; otherwise change route or stop | Responsible party closes the gap and repeats the test; otherwise change route or stop | A small test does not guarantee full-scale year-round performance. |
| C Factory acceptance test | Manufacturer executes; owner or third party witnesses as contracted | Actual manufacturing configuration and instrument calibration clear | Serial number, configuration, control, alarms and no-load and load records | Contract FAT clauses and safety and control items pass | Manufacturer repairs and retests | Actual wastewater performance. |
| D Delivery and installation | Site party installs; manufacturer checks requirements; owner organises delivery | Civil works, utilities and maintenance space complete | Delivery, shortage, material and instrument certificates and hidden-work records | Drawings, supply list and installation specification pass | Correct by manufacturer, site party or owner responsibility | Interconnection or biological performance. |
| E Clean-water and interconnection | Manufacturer and site party jointly; owner supplies utilities and operators | Installation, electrical, instrument and safety conditions complete | Point-by-point I/O, pumps and blowers, level, interlocks and fault stop | All agreed I/O, interlocks and safety functions pass | Correct by defect responsibility | Load capacity or biological performance. |
| F Biological start-up | Manufacturer or process party tunes; owner stabilises feed, personnel and disposal; site party closes leftovers | Interconnection passed; sludge or seed, transport and return interfaces available | Daily flow, load, DO, sludge, effluent and abnormalities | Repeatable safe operation; root causes corrected | Manufacturer or process party retunes, owner restores feed and disposal, and the responsible party corrects; repeat the start-up check | Start-up is not completed performance acceptance. |
| G Representative performance verification | Owner holds the agreed conditions; manufacturer operates and guarantees; third party or agreed laboratory tests | Peak, average, low load, recovery and series exit are assigned as guaranteed or not guaranteed conditions | Synchronised flow and load, composite samples, online curves, stock, bypass and energy or chemical records | Agreed effluent, capacity, disinfection, residuals and availability pass together | Correct and retest by responsibility | A season or condition that did not occur is not written as verified. |
| H Training and handover | Manufacturer trains and hands over documents; owner provides personnel; site party hands over completion records | Defects closed or remaining items have an owner and deadline | Practical assessment, SOP, spare parts, drawings and software versions | Personnel can operate the agreed system; documents and spares complete | Manufacturer adds training or documents; owner adds personnel and procedures | Unattended operation or maintenance-free running. |
| I Long-term compliance | Owner records and maintains; manufacturer supports under warranty; third party checks as required | Handover complete; consumables and transport resources available | Trends, permit samples, sludge and reuse records, maintenance and abnormalities | Permit and contract requirements continue to be met | Correct by contract and root cause; a trend limit triggers review | Initial acceptance does not replace long-term permit responsibility. |