Construction of the company's industrial high-temperature heat pump and high-efficiency drying equipment project started on 2023-12-02. The reports record total investment of RMB 360 million and describe the project as co-invested with Guangdong Furuise.
Reported figures
Wide table: scroll sideways to see every column.
| Item | Reported figure | Status |
|---|---|---|
| Groundbreaking | 2023-12-02 | Reported event |
| Total investment | RMB 360 million | Reported investment figure |
| Site and building area | 40,000 m² site; 30,000 m² building area | Reported project scale |
| Equipment | 120+ sets | Reported equipment count |
| Planned annual capacity | 1,500 heat pump units and 200 drying equipment sets | Planning target at full capacity |
| Planned annual sales revenue | RMB 400 million | Planning target, not actual revenue |
| Planned annual tax and profit | RMB 16 million | Planning target, not actual result |
Planning targets
The capacity, revenue and tax-profit figures represent the level planned at full capacity. They are planning targets, not current output, current sales or audited results.
Later reporting
In October 2024 local media reported that the phase I workshop had entered trial production. The same reporting described the revenue figure as a target. The project as a whole is not recorded as complete.
Sources and verification
- The December 2023 groundbreaking reports record the date, investment and planned capacity.
- The October 2024 reports record the trial-production statement; the revenue figure is read as a target.
- Actual output, sales and tax figures are governed by operating records and audited statements.